Rebuilding Governance for a Public Infrastructure Authority
A regional public infrastructure authority overseeing multiple concurrent transportation and utility capital projects.
We named who decides what across the authority's capital program, and program-level decisions now take roughly 35 percent less time.
Situation
Public infrastructure authorities answer to a standard that commercial capital programs seldom face. Legislative oversight bodies and the public examine how contracts are awarded and how contractors are held to account. Informal decision-making that would pass unnoticed in a private company becomes hard to defend.
This authority's program had expanded quickly. Ownership of procurement decisions, schedule escalation and contractor oversight had settled informally within each project team. Practice varied from project to project, and the internal audit said so.
What we did
We first mapped how decisions were taken in practice across every active project. From that we built a program-level operating model with a decision-rights framework, which states who owns each type of decision.
| Decision area | Before | After |
|---|---|---|
| Procurement | Interpreted by each project team | Named owner at program level |
| Schedule escalation | Informal and inconsistent | Defined escalation path and owner |
| Contractor oversight | Different practice on each project | One prequalification and performance-monitoring framework |
Impact
- Decisions at program level are reached in about 35 percent less time now that each has a named owner. The comparison is with the authority's own cycle before the new model.
- Every active project applies the same standard for prequalifying and monitoring contractors.
- The authority can explain its oversight model to auditors, regulators and the public in the same terms on every project.
What made it work
We described the existing practice before proposing a new one. Project teams recognized their own work in the map, which made the gaps hard to dispute.
Each project's own approach to contractors may have been reasonable. Only a single standard, used on all of them, can be defended under public scrutiny.
Program-level decision cycle time compressed by approximately 35 percent
One contractor prequalification and monitoring framework on every active project
The internal audit finding on contractor oversight addressed
- Sector
- Government & Public Infrastructure
- Practice area
- Transformation & Organization
- Client profile
- Regional authority running transportation and utility capital projects
- Services
- Program operating model, decision rights, contractor oversight framework
- Key phases
- Mapping of every active project; authority-wide rollout
This case study is a composite drawn from multiple engagements. Client details have been changed and combined to protect confidentiality, and figures are representative rather than attributable to any single client.
Facing a comparable challenge?
Tell us about your organization and we will route you to the right partner.
Standardizing Rig Move Execution Across a Fleet
Read case study →Redesigning Shift Operations Around Actual Workflow
Read case study →Realigning Sales and Delivery Around the Customer Journey
Read case study →A Scalable Job Architecture for a Multi-Acquisition Firm
Read case study →Building Leadership Capability Ahead of Scale
Read case study →A Right-Sized HR Operating Model for Current Scale
Read case study →The Hidden Cost of an Undocumented Operating Model
The org chart shows how work was meant to flow. How it really flows is usually written down nowhere.
Rig Move Efficiency Is a Leadership Problem
The gap between a fast rig move and a slow one is set in planning and briefing, well before the first truck arrives.
Designing Operations Around the Customer Experience
Customers do not see departments. They see what happens to their order as it passes between them.